Replacement of screw screens

Oct 9, 2020

In recent days, we had two major projects to carry out, with the replacement of screens from competing brands, and what is more of different technology.

A difficult exercise for several reasons:

– the taking of odds carried out by our sales representatives must be mastered,

– our technical and financial offer must highlight all the advantages of our solution,

– our design office must identify the customer’s needs and optimize operations,

– finally, our technicians must be quick and efficient before training the staff on our technology during commissioning.

After a few hours of operation, comparisons and comments from operators did not drag on. The equipment is quieter due to the absence of washing ramps but also much more compact. Important advantages when the screens are in a room. Water consumption is zero since the PROSTEP type screen operates without water supply. And finally, no more tedious replacement of brushes and strainers to be expected.

Do not hesitate to contact us if you have similar needs.

The entire FB Procedes team is at your disposal.

 

TECHNICAL DATA

Project in the South of France

Replacement of 2 Screw Sreens of competitor brand by 2 Screens type PROSTEP

  • STAINLESS STEEL 316L
  • Maxi flow rate per Screen 600m3/h
  • Bar spacing 4mm
  • Channel depth 700mm
  • Channel width 700mm
  • 3 days of intervention
  • Options retained: waste chute, supply of a piston press with its adaptation chute, dismantling of the existing and assembly of the new one carried out by an FB Procedes technician, training of operating personnel.

Project in the North of France

Replacement of one Screw Screen of competitor brand by one Screen PROSTEP

  • STAINLESS STEEL 304L
  • Maxi flow rate 190m3/h
  • Bar spacing 6mm
  • Channel depth 1460mm
  • Channel width 700mm
  • 1 day of intervention
  • Options retained: maintenance jib crane, waste evacuation chute, upstream / downstream “radar” probes, FB Procedes electrical control panel, assembly carried out by an FB Procedes technician and training of operating personnel.

PROJECT PHOTOS

dégrilleur en canal

South project

Site before FB Procédés intervention

dégrilleur en canal

South project

Disassembly of the Screw Screen

dégrilleur en canal

South project

Entrance of the Screen type PROSTEP in the room

dégrilleur en canal

South project

The space saving is clearly visible

dégrilleur en canal

South project

The 2 PROSTEP are installed

dégrilleur en canal

South project

The piston press installed under the 2 Screens

dégrilleur en canal

North project

Site before FB Procédés intervention

dégrilleur en canal

North project

Approach of PROSTEP above the channel

dégrilleur en canal

South project

Downstream view

dégrilleur en canal

South project

Upstream view with electrical control panel